Current Public Works Projects

VIEW THE 2012 PUBLIC WORKS REPORT

VIEW PAST REPORTS TO THE COUNCIL

* PLEASE NOTE
– The table below represents the most up-to-date project information. Projects listed are those that meet the criteria for bidding. This list does NOT include in-house projects or complete information on recreation, waterworks or government building projects.

UNDER CONSTRUCTION
PROJECT NAME
DISTRICTFINAL COST
GRANT / LOAN
East Bank Levee Bike Path, Phase IV, Harding St. to Apple St. All $287,000 $287,000
East Bank Levee Bike Path, Phase V, Apple St. to Spillway All $243,900 $243,900
Fifth Street Norco Sidewalk and Other Improvements6$326,328 $250,000
West Bank Levee Path Phase IIIb – Diversion to Jeff ParishAll$928,000$881,700
2012 Road Maintenance All $1,490,000 -
Dunleith Canal Sheetpile Stabilization Phase III 3 $900,000 -
Montz Master Drainage Plan - Improve KCS Canal6$770,000-
Community Center Project
All$10, 565, 980
-

COMPLETED PROJECTS
PROJECT NAME
DISTRICTFINAL COST
GRANT / LOAN
LCDBG East Bank Street Improvements
3, 5$469,114$406,491
Destrehan WWTP Rehab Phase I3, 5, 6$349,500-
Destrehan WWTP Rehab Phase II3, 5, 6$268,950-
Ama Pump Station Bar Screen Cleaner and Deck2$1,580,100-
2008 Road Maintenance ContractAll$973,569 -
Montz MDP - Evangeline Rd. Culvert Install6$148,988 $142,800
2009 Road ManualsAll$70,000 -
Maryland Drive Conspan Bridge Crossing 7$455,022-
Courthouse Emergency Generator All$992,200$358,228
Beaupre and Lakewood Sewer Improvements 2$827,975-
Cousins PS Bar Screen Cleaner and Deck 2, 7$3,528,286$3,521,819
Paradis Pump Station Bar Cleaner and Deck 4 $910,513 $750,000
Replace Pump and Install Cover - New Sarpy Pump Station
6$247,300-
Schexnayder Pump Station Bar Cleaner and Deck 3, 6 $2,163,567 $869,151
2009 Road Maintenance All$726,762-
Rathborne Park Walking Trail
2, 7$90,385$90,385
Montz MDP - Replace Culverts Thoroughbred Lane6$259,865-
Replace Natural Gas Engines Destrehan I PS3$444,000-
Public Works / Wastewater Office Relocation      All $557,665 -
Dunleith Canal Sheetpile Stabilization Phase I3$900,000-
Replace Culverts Michael Drive4$179,496
Acorn and Sharon Sewer Improvements 7$479,348$479,348
West Bank Levee Bike Path, Phase II, Elm St. to Davis DriveAll$1,338,192$1,318,582
West Bank Levee Bike Path, Phase III, Davis Dr. to DiversionAll$208,863$141,749
East Bank Levee Bike Path, Phase II, Ormond Blvd. to Harding St. All$265,577$320,000
Lakewood Automatic Bar Screen Cleaners 7 $1,297,217$1,448,724
Upgrade Boutte Pump Station 1$810,453-
Install Gates on Hwy. 61 Culverts / Prescott PS7$265,000-
2010 Road MaintenanceAll 
$1,899,932-
West Bank Shop Building                         
All            
$570,800
-
Ormond Boulevard Culvert Replacement3$2,187,218$2,187,211
Engineers Canal PS Automatic Bar Screen Cleaner6$1,607,426$1,897,934
Dianne Pump Station Automatic Bar Screen Cleaners5$653,900$603,900
New Sarpy Pump Station Bar Screen Cleaners 6      $1,741,991 $1,640,000
Hahnville Wastewater Plant Rehabilitation of Coatings All $397,715 $397,715
Coronado Pump Station No. 2 Upgrade7 $796,660-
Courthouse HVAC Project All  $537,000 $353,000
2011 Road Maintenance All $1,400,000 -
Eighty Arpent Pump Station Bar Screen Cleaner and Upgrade1 $6,997,031$6,967,930
Destrehan Wastewater Plant Rehabilitation Phase III and Phase IV
3, 5 ,6 $1,070,000Loan: $1,070,000
Hahnville Wastewater Plant Rehabilitation Phases I-IV            1, 2 ,4 ,7 $1,347,000Loan: $1,347,000
High Priority Lift Station Upgrades (6) 2, 7 $1,510,228Loan: $1,510,228
Willowdale Box Culverts
2$549, 275
$549, 275
No. 10 Canal Canal Road Crossing Culverts 4$1,600,000$1,600,000
Dunleith Canal Sheetpile Stabilization Ph II
3
$1,418,440
-
Spillway Road Resurfacing6$489,700-
Destrehan II Pump Station Access Bridge3$222,295-
Eighty Arpent Pump Station Upgrade1 $2,970,000 $2,967,030
Eighty Arpent Pump Station Auto Bar Screen Cleaner 1
$4,110,000 $4,000,900
New Sarpy Water Plant AdditionAll 
$28,886,515 

Hwy. 631 Cast Iron Water Line Replacement    
4
$642,610 $675,950

IN FINAL DESIGN PHASE
PROJECT NAME
DISTRICTESTIMATED COST
GRANT / LOAN
Coronado Park Drainage Improvements and PS
7
$1,206,540
App. Submitted
Primrose Canal Crossing Improvements
7
$1,381,050
$1,137,029
Cajun Paradise Levee
4
$920,000
-
Oakland / Fairfield Drainage Improvements
5
$2,200,000
App. Submitted
Canadian National Trestle Replacement Projects
-
-
-
Mimosa Drainage Improvements
7
$749,410
App. Submitted

Chart updated December 27, 2012

LCDBG
= Louisiana Community Development Block Grant
PS = Pump Station
MDP = Master Drainage Plan
CBS = Canal Bank Stabilization

Last updated: 12/28/2012 8:52:48 AM