READ THE LATEST WEST BANK HURRICANE PROTECTION LEVEE UPDATE

Post Date:September 15, 2017 9:17 a.m.

Willowridge Reach

  • The Willowridge Levee Phase 1 earthen levee project is complete.
  • Willowridge Pump Station: All the three pump’s impellers have been replaced and the pumps were retested. The effective date for Substantial Completion for this project is Aug 29, 2017. The Substantial Completion document has been executed and Filed at the SCP Courthouse. Contractor has been working on the final punch list items. The Final Change Order and Final Acceptance of the project are being developed.
  • Willowridge Phase III: Substantial completion of the project was granted on May 8th, 2017. Certificate of Final Acceptance has been fully executed with an effective date of Aug 9, 2017. The project has been accepted and is completed.

Ellington Reach

  • Ellington Levee – Phase I Project: As of this Council Meeting is the project is 627 into the 730 calendar day project. The anticipated completion date is in December 2017. The Contractor has initially completed clearing and grubbing operations, inspection trench along the project length, Truck Wash-down Racks at Magnolia Ridge and Valencia Dr. entrances, timber matting over the existing gas pipe lines at the shell road off of Magnolia Ridge Road and at other two gas pipeline crossing locations, Valencia culvert and Magnolia Ridge culvert with sluice gate. Contractor has installed the new drainage canal culvert crossing at Magnolia Ridge and Valencia Dr. Contractor is continuing to perform canal excavation, and placing embankment. In Area 5, the eastern portion of the project, the +7.5’ elevation levee embankment, access roadway, drainage canal and seeding, fertilizing and mulching operations have been completed. The Levee embankment for the Ellington Levee – Phase I Project is progressing at an accelerated level during this period of dry weather. Levee embankment construction is completed to the +7.5’ elevation for 2,500 ft and the remaining 8,000 ft of Levee embankment has been constructed to the +4.5’ elevation or greater. Of the total of 147 certification test required for Levee Certification in this project, 94 test have pass and have been accepted. This represents a 64% completion of passed and approved certification tests for levee embankment for this project.
  • The Ellington Levee – Phase 2: Project is nearing completion of final design. The Engineer has submitted 90% final plans and specifications to Public Works for review. The Ellington SFM has been completed, but the bid advertisement for the Ellington Levee - Phase 2 is awaiting completion of Ellington Levee Phase-I project.
  • The 90% final design documents for the Ellington Pump Station have been submitted to the Parish for review. Received notification from DOTD Statewide Flood Control Program advices that this project will appear in the FY 2017/18 recommended construction program.

Magnolia Ridge Reach

  • Magnolia Ridge Levee:Geotechnical Engineer has taken approx. 65 soil borings along the alignment of the existing levee to analyze for suitability to cap the existing levee and bring the low spots to elevation +7.5. The analysis is to verify if the existing levee meets the latest USACE levee criteria. Analysis is complete and the geotechnical report has been provided to BKI for incorporating into the final design of the Magnolia Ridge levee Project. BKI has begun preparing the final design plans and specification.
  • Magnolia Ridge Pump Station: HMGP funding has been awarded to the project, and the project has been approved in FEMA’s project tracking system. Currently awaiting on FEMA’s official approval letter. Advertisement for bidding of this project is scheduled to begin on 9/14/17. Advertisement for bidding of this project has begun on 9/14/17. The Mandatory Pre-Bid Meeting for the Magnolia Ridge Pump Station Project is scheduled for 10:00am on October 3, 2017 at the Public Works Office.

Sunset Reach

  • Parish has acquired 21 of 30 levee servitude parcels from 27 impacted landowners. GCR met with owner of Parcel 27-4 on Wednesday, September 13, 2017 and provided the Just Compensation Offer package, including Residential Relocation Assistance documentation. GCR also conducted the residential occupant interview and house inspection for the required mobile home relocation. GCR is working to prepare the relocation plan. The Parish is moving forward with the agreement with Chevron for acquisition of its four parcels which contain 34.21 acres of levee right of way. Two parcels (Dufrene) have been recommended for expropriation and are awaiting Parish Council approval. GCR is currently preparing two pre-litigation files for two previously authorized expropriation.